Capital Improvement Program

Indian Trail has 25 projects in its Capital Improvement Program (CIP). These projects will help maintain or improve infrastructure throughout the Town over the next several years. The chart below lists the projects, their estimated costs and timeline for completion. Projects with an end date of July 1, 2020, are continual and do not yet have a solidified end date. The July 1 date is given for budgetary purposes. All other projects have a projected end date already set. 
Project Total Cost of Project Start Date/Phase Targeted Completion Date
Monroe Rd. Widening
$46,600,000
RE Acquisition Phase December 2025
Sardis/U-IT Roundabout
$3,202,825
Utility Relocation Phase Aug. 21, 2020
Independence BV Superstreet
$9,500,000
Construction Phase Nov. 30, 2019
Chestnut Parkway Phase III
$3,629,054
Design Phase June 30, 2025
Chestnut Parkway Phase II
$86,145
RE Acquisition Phase June 30, 2022
Indian Trail Complete Street
$3,972,419
Design Phase Jan. 1, 2021
Resurfacing FY 19/20
$1,239,369
Complete (under budget) Oct. 31, 2019
Pavement Marking
$15,000
Complete (under budget) July 30, 2019
Pavement Marker
$15,000
Complete (under budget) July 26, 2019
Pavement Patching
$187,900
Complete (under budget) Aug. 9, 2019
Crack Pouring
$30,000
Complete (over budget) Aug. 9, 2019
Town Hall Parking Lot
$300,000
Complete (under budget) Aug. 30, 2019
Gribble Roundabout
$1,518,270
Planning Phase June 30, 2022
Regulatory Signage
$3,098
Construction Phase July 1, 2020
Rogers Road Improvements
$390,000
Design Phase Dec. 30, 2020
Bridge Maintenance
$61,968
Construction Phase July 1, 2020
Chestnut Park Artificial Turf
$877,000
Complete (under budget) Oct. 7, 2019
Crooked Creek Park Phase II
$1,950,000
Design Phase December 2020
Highway 74 Multi-Use Trail
$5,130,131
Design Phase December 2020
Greenway Trail
$0.00
Design Phase December 2020
Storm Drainage Maintenance
$250,000
Complete (at cost) July 1, 2020
1st Avenue Storm Drainage
$913,849
Design Phase Oct. 30, 2019
1st Avenue Construction
$984,414
Design Phase July 1, 2020
IT Park Design
$32,000
Design Phase Jan. 1, 2020
IT Park Construction
$425,000
Design Phase July 1, 2020